What Rio Rancho's Proposed Rec Center on 9th Avenue Would Include, and How to Weigh In

November 5, 2026

Near Northern Boulevard and Rockaway, on a 13-acre lot at 4477 9th Ave. NE, part of the old school parking lot is still there. Stapleton Elementary used to stand on this site, and Shining Stars Preschool came after it. Homes border the property, and the main library and the Rio Rancho Aquatic Center are close by. The City of Rio Rancho wants to build its proposed Multi-Generational Recreation Center here. On Monday, Nov. 9, residents get their first public look at the latest design.

The plan is smaller and more focused than it was a year ago, and it is still early. The only money identified so far is for design, so the open house comes while the plan can still change.

A site chosen for its neighbors

The city has a long history with this land. At the Oct. 19, 2026, Parks and Recreation Commission meeting, staff explained that the city leased the site to Albuquerque Public Schools in 1989 on a 99-year lease for Stapleton Elementary, and that it later became part of Rio Rancho Public Schools. Shining Stars Preschool moved in after that. Once the preschool built a new facility and moved out, the site went back to the city. The Sandoval Signpost now describes the 13 acres as city-owned. City staff told the Parks and Recreation Commission on Oct. 19, 2026, that the land is zoned R1, so the project would need a rezoning before anything gets built.

The location explains a lot about the design. With the library and the Aquatic Center nearby, the new building doesn't have to do everything. It can cover what that part of the city is missing.

What Phase 1 and Phase 2 would put on the ground

The city plans to build in two phases. Each phase is a meaningful project on its own.

Phase 1, estimated at $42.6 million

  • A 49,140-square-foot building built around a multisport gymnasium
  • Locker rooms, restrooms and a small administrative area
  • Outdoor basketball courts
  • Walking trails, parking and circulation

Phase 2, estimated at $33.8 million

  • 33,534 more square feet with gymnastics and climbing space
  • Fitness and cardio rooms, multipurpose rooms and a stage
  • A café or snack and gathering area, plus more lockers
  • Outside: two tennis courts, ten pickleball courts, two play areas designed for different age groups, an agility course, open lawn for gatherings, and more parking

The concept also sets aside areas for stormwater and landscaping. Altogether, the two phases add up to 82,674 square feet of building space on the site.

Phase 1 puts a gym, basketball courts and trails on the site. Phase 2 brings everything else people tend to picture when they hear "rec center," including the climbing wall, the fitness rooms, the stage and the pickleball courts. If funding arrives one phase at a time, the first opening day would mostly be about courts.

What changed since 2025, and why there's no pool

The current concept looks quite different from the one staff showed the Governing Body at a work session on Aug. 19, 2025. No formal votes were taken at that meeting.

August 2025 concept October 2026 concept
Building Two-story program Two phases, 82,674 sq ft total
Signature features Indoor track, fitness center, rooftop deck Multisport gym, gymnastics and climbing, stage, café
Outdoor Tennis, pickleball and basketball courts, playground, agility course Basketball, two tennis courts, ten pickleball courts, two play areas, agility course, walking trails
Parking 422 spaces Phased, added in both phases
Estimate $104,175,482.38 $76,363,850, in 2026 prices

Back in 2025, staff suggested building in pieces of roughly $25 million each. The 2026 version replaces those smaller pieces with two larger phases and brings the total down by about $28 million.

Aquatics is the most noticeable thing missing. At the Oct. 19 commission meeting, a commissioner asked whether the city had considered adding therapy aquatics. Staff said they had, but because the Aquatic Center is just up the street, they decided not to put aquatic amenities at this location. Staff also said they would note the suggestion. The question has already come up in a public meeting, and residents can raise it again at the open house.

The money, and the clock that comes with it

Only one dollar figure has funding behind it so far. According to the Oct. 19 Parks and Recreation Commission meeting record, the only money identified for the project is about $2.5 million for design, and nothing has been set aside yet for the building itself. Staff said the city would look at the general fund, grants and the Legislature. The Sandoval Signpost put it more bluntly, listing zero dollars currently identified for construction.

The estimates are also tied to the calendar. City staff priced both phases in 2026 dollars and told the commission to plan for roughly 4% inflation per year. At that rate, a $76.4 million project goes up about $3 million a year. That is more than the entire $2.5 million design budget. After one year, the combined estimate would be around $79.4 million, and after two years, around $82.6 million.

The schedule shows why those years add up. The October presentation estimated about 18 months for design and about 18 months for construction once funding is in place. The Signpost reported that Phase 1 design should be finished in early 2028 and that construction depends on finding the money. As of the Oct. 19 meeting, the commission had made no formal decision on the center. Commissioners named Nov. 9 as the next step for public engagement.

In short, the city has a design it is willing to show, money to finish that design, and no construction funding yet. A project at this stage can still change, and residents are being asked to help decide how.

How to weigh in on Monday and after

The city calls the event a Community Open House: Proposed Multi-Generational Center. It's a drop-in format with informational displays and conceptual designs. There won't be a formal presentation, so you can stop by whenever it suits your evening.

To make the most of a few minutes at the displays, it helps to think about phasing. Phase 1 is the gym, basketball courts and trails. The pickleball courts, climbing space, fitness rooms and stage all come in Phase 2. If something on the list matters to you, the open house is a good place to say whether it belongs in the first phase. The aquatics question is still open too, since staff took a note on it in October and haven't closed the door.

Cindy has been following projects like this around Rio Rancho for close to three decades. She's happy to talk through what's planned near Northern and Rockaway and how city plans like this one fit into your own plans for staying or moving. When you're ready, reach out to Cindy Chavez. Let's Connect.